Sri. Balasimha Rao v. the Karnataka Renewable Energy Development Limited (Kredl)
Case brief
What is this about?
Delay and laches; alternative remedy doctrine; appeal to APTEL under Section 111 Electricity Act 2003; KERC order under Section 86(1)(f); Karnataka Solar Policy 2014-21; solar PPA tariff Rs.8.40 per unit versus Rs.6.51 per unit; LoA received after 31.08.2015 cut-off; Red Earth Green Energy v. KPTCL (KERC OP 63/2017); Murrali M Baaldev v. KREDL (APTEL Appeal 207/2017); scope of Article 226 exceptions to alternative-remedy rule as per L.K. Verma v. HMT Ltd. (2006) 2 SCC 269; writ dismissed at threshold on twin grounds of delay and non-exhaustion of remedy; merits of tariff discrimination left undecided. Single Judge: Ravi V Hosmani J.
What did the court decide?
The impugned order was passed by KERC under Section 86(1)(f) of the Electricity Act, 2003 and was appealable before APTEL under Section 111 thereof. ¶65