M/S L P D Solar Power Private Limited v. Sri Baji Sab
Case brief
What is this about?
Solar power plant transmission line compensation; Section 16(3) Indian Telegraph Act 1885 claim before District Court; diminution of land value at 30%; electricity poles versus transmission towers; corridor area 4.447 guntas; per-pole compensation of Rs.10,000/- held without basis and reduced; litigation costs over and above compensation; 8% interest from date of petition till payment; W.A.no.1735/2024 (Division Bench, 21.07.2025) relied upon; Kaluvehalli village, Challakere Taluk, Chitradurga; BESCOM power purchase agreement dated 29.06.2015; 2 MW solar plant Sy.no.193/5; writ petition under Articles 226 & 227; impugned order modified, petition allowed.
What did the court decide?
Writ petition allowed; impugned order dated 20.11.2021 in Civil Misc.No.752/2019 modified — respondent entitled to Rs.2,501/- (corridor area), Rs.56/- (area under 4 electricity poles) and Rs.10,000/- (litigation costs), with interest at 8% per annum from date of petition till payment; amount in deposit to be transmitted to the District Court for payment, excess if any to be refunded to petitioners.