Sri Ashok Kumar S v. State of Karnataka
Case brief
What is this about?
BBMP Act 2020; Section 248(1) provisional order; merger of provisional order in Section 248(3) final order; Sections 248(3) and 356 orders; Section 356(1) follow-up order; Section 240(8) post facto sanction / regularization of construction put up without plan; communication dated 30.07.2025 directing disconnection of water supply; writ disposed with liberty to appeal to appellate authority within 15 days; interim restraint on respondent No.4 (Assistant Executive Engineer, BBMP Rajarajeshwari Nagara Division); Zonal Commissioner BBMP; Articles 226 and 227 of the Constitution; unauthorized construction; show cause notice Section 248(2).
What did the court decide?
Writ petition disposed of, directing the petitioner to approach the appellate authority against the order passed under Sections 248(3) and 356 of the BBMP Act, 2020, the appeal to be filed within 15 days, with liberty to seek interim relief in that appeal; until the appeal is filed and till 15 days from now, respondent No.4 shall not give effect to the communication dated 30.07.2025 addressed by respondent No.3 (such interim protection being solely to enable filing of the appeal); memos of appearance permitted to counsel for respondent Nos.2 and 3 and the Additional Government Advocate within ten days.