M/S Nandi Builders and Developers v. Bangalore Electricity Supply Company Limited
Case brief
What is this about?
Karnataka High Court, Bengaluru; WP No. 3197 of 2025 (GM-KEB); Justice Ravi V Hosmani; decided 04-08-2025; BESCOM permanent electricity connection; writ of mandamus; representation dated 20-11-2024 (Annexure-V); sanction order dated 25.06.2024 (Annexure-R2); compliance with Supreme Court directions in Rajendra Kumar Barjatya v. U.P. Avas Evam Vikas Parishad, (2024) SCC OnLine SC 3767, para 21; completion/occupation certificate precondition for service connections; BDA no-objection certificate; joint development agreement; petition disposed of with two-week timeline for BESCOM action upon compliance report.
What did the court decide?
Direction to respondents no.1 and 2 to take necessary action within two weeks from the date the petitioner reports compliance, under acknowledgement to the respondents, such compliance covering the specifications in Annexure-R2 and the direction in para no.21 of the Supreme Court's decision in Rajendra Kumar Barjatya v. U.P. Avas Evam Vikas Parishad.