Mr L N Srinivasa Murthy v. State of Karnataka
Case brief
What is this about?
Karnataka HC (Bengaluru), W.P. No.3127 of 2025 (LA-KIADB), K.S. Hemalekha J., 13.11.2025 — KIADB acquisition, Doddaballapur Taluk, Bengaluru Rural District: 14-year unexplained gap between S.28(1) preliminary notification (09.06.2010) and S.28(4) declaration (01.10.2024) vitiated the acquisition; S.28(3) enquiry summary and mechanical (no application of mind to fertility, residential structures, 2007 Circular); declaration and SLAO order quashed and preliminary notification declared lapsed qua Schedule 'A' (Sy.No.211/2); compensation for Schedule 'B' (Sy.No.250/1) to be determined under S.29 KIAD Act with 2013 Act provisions at market value as on 08.09.2023; de novo acquisition permitted. Keywords: KIAD Act S.28; staleness of preliminary notification; inordinate delay; natural justice; RFCTLARR Act 2013; Article 300A; C. Padma; K.S. Chandrasekhar; Malligamma.
What did the court decide?
Writ petition allowed: (i) declaration dated 01.10.2024 under Section 28(4) of the KIAD Act and order dated 24.06.2024 under Section 28(3) quashed insofar as they relate to Schedule 'A' property, Survey No.211/2 measuring 2 acres 3 guntas, Linganahalli Village, Kasaba Hobli, Doddaballapur Taluk; (ii) preliminary notification dated 09.06.2010 under Section 28(1) declared to have lapsed on account of inordinate and unexplained delay; (iii) respondents to determine and disburse compensation for Schedule 'B' property (Sy. No.250/1 measuring 2 acres 22 guntas) in accordance with Section 29 of the KIAD Act by applying the provisions of the 2013 Act, based on market value as on 08.09.2023; (iv) respondents at liberty to initiate de novo acquisition proceedings for Schedule 'A' property in accordance with law.