M/S Micro Labs Limited v. State of Karnataka
Case brief
What is this about?
Micro Labs Limited; 10 MW wind power generation project; Lingasuguru and Manvi Taluks; Wheeling and Banking Agreement (WBA) executed 31.10.2023; KERC (Terms and Conditions for Green Energy Open Access) Regulations 2022 struck down in W.P.No.11235/2024 (disposed 20.12.2024); KERC (Terms and conditions for Open Access) Regulations 2025 stayed in WP No.201341/2025; representation dated 23.07.2025 bearing No. MLL/WIND PROJECT/003-2025 (Annexure-Z); writ of mandamus to consider representation; direction to respondents no.4 and 5 (Karnataka Renewable Energy Development Limited and State Load Dispatch Centre Karnataka) to consider within 4 weeks and intimate result; Karnataka Power Transmission Corporation Limited; Gulbarga Electricity Supply Company Limited; State of Karnataka Department of Energy; NC: 2025:KHC:35507.
What did the court decide?
Direction to respondents no.4 and 5 to consider petitioner's representation dated 23.07.2025 at Annexure-Z in accordance with law within 4 weeks from the date of the order and intimate the result of consideration to petitioner.