Sri. B. S. Suresh v. Bruhat Bengaluru Mahanagara Palike
Case brief
What is this about?
Writ petition (certiorari) under Articles 226/227, High Court of Karnataka, against BBMP Assistant Executive Engineer's order dated 07.07.2025 disconnecting electricity to a building under construction in Bellandur/Marathhalli area, Bengaluru, following action under Sections 248(1), 248(2), 248(3) and 356(1) of the Bruhat Bengaluru Mahanagara Palike Act, 2020 for construction allegedly not in accordance with the sanctioned plan; Court held non-filing of the statutory appeal within 30 days justified disconnection, but permitted belated appeal and ordered BESCOM to restore supply to R.R.No.7SKTP28863 subject to a no-further-construction condition, with liberty to BBMP to seek sealing/stopping of construction and a 15-day window for filing the appeal; decided 26.11.2025 by R. Nataraj, J.; keywords: BBMP Act 2020, unauthorised construction, electricity disconnection, restoration of power supply, appellate authority, interim protection.