M/S Bagmane Developers Pvt. Ltd. v. the State of Karnataka
Case brief
What is this about?
Bagmane Developers Pvt Ltd | KIADB | BMRCL | Bangalore Metro Rail Corporation | Metro Rail Project land acquisition | compensation entitlement | Section 30 and 31 Land Acquisition Act 1894 | endorsement dated 23.08.2019 | notice dated 16.09.2019 | Memorandum of Understanding dated 19.01.2010 | clause 24 dispute resolution | conciliation and sole arbitrator | Arbitration and Conciliation Act 1996 | representation dated 21.11.2022 | writ petition disposed with liberty | Articles 226 and 227 Constitution of India | High Court of Karnataka | WP No. 26132 of 2022 (LA-KIADB) | Justice M.G.S. Kamal | 27 January 2025
What did the court decide?
Liberty to the petitioner to pursue such remedy as may be available under law in furtherance and in terms of clause 24 of the Memorandum of Understanding dated 19.01.2010, as sought for; no other relief granted and the impugned endorsement and notice were not quashed.