Vishweshwaraiah v. Executive Engineer (Ele.) (v)
Case brief
What is this about?
Karnataka High Court 2025; BESCOM; execution of award/work order U-13178 dated 30.11.2018 modified 06.08.2019; irrigation infrastructure; Akrama Sakrama scheme; UNIP RR no.NSIP 8103; writ of mandamus; police protection against obstruction; delay/inaction in executing work order; payment of Rs.16,610; Tumakuru/Gubbi/Nittur; Articles 226 & 227 Constitution of India; single judge Ravi V Hosmani.
What did the court decide?
Direction to respondents no.1 to 4 to execute award and work order bearing no.U-13178 dated 30.11.2018, with modifications on 06.08.2019 as per Annexure-E, if necessary by taking police protection in case of any obstruction, within an outer limit of three months from date of receipt of certified copy of the order. ¶47