Shri. Kumar Hattikal v. the State of Karnataka
Case brief
What is this about?
writ petition; mandamus; Articles 226 and 227; work done certificate; tender amount payment; road construction contractor; successful bidder; representation dated 26/03/2025 Annexure-F; Executive Engineer RDPR Haveri; State of Karnataka Rural Development and Panchayatraj Engineering Department; consideration within reasonable time; eight weeks; GM-TEN; Karnataka High Court Dharwad Bench; Pradeep Singh Yerur
What did the court decide?
Writ of mandamus issued directing respondent No.2 to consider the petitioner's representation dated 26.03.2025 and pass suitable orders in accordance with law within a time period of eight weeks from the date of receipt of copy of the order. ¶37