M/S Chandragiri Construction Company v. the State of Karnataka
Case brief
What is this about?
Bare dismissal of a Regular First Appeal challenging a money-recovery decree (OS No.46/2010, Principal Senior Civil Judge and CJM, Mangaluru, decree dated 08.06.2023); appeal filed under Sec.96 r/w Order 41 Rule 1 CPC by M/s Chandragiri Construction Company (adv. Sri. Dineshkumar Rao K) against State of Karnataka Ports and Fisheries Department officials; High Court of Karnataka, Bengaluru, dismissed the appeal on 19.09.2025 solely because office objections were not complied with, in view of its peremptory order dated 15.02.2024; no merits argued or decided, no cases cited, no amounts; bench: Anu Sivaraman and Rajesh Rai K, JJ.
What did the court decide?
In view of the peremptory order dated 15.02.2024 passed by this Court, no further order was required. ¶32