Board of New Mangalore Port Authority v. M/S. Ccc Builders Merchant Pvt. Ltd.
Case brief
What is this about?
Karnataka High Court (DB, NC: 2025:KHC:4366-DB), MFA No. 5841 of 2024 (AA), decided 30.01.2025. Board of New Mangalore Port Authority v. M/s CCC Builders Merchant Pvt. Ltd. & Anr. (Justice N. Kumar, sole arbitrator). Keywords: appeal under Section 37(1)(c) of the Arbitration and Conciliation Act; condonation of delay of 25 days under proviso to Section 34(3); petition under Section 34 beyond three months but within thirty days; insufficient cause and mandatory pre-reference notice under Section 34(5) sent 17.03.2023; date of receipt of award 28.11.2022 for computing limitation; arbitral award dated 12.08.2022 in AC No.69/2020; reliance on Mehta Construction Company (2022) 5 SCC 432; restoration/remand to District Judge Mangalore for decision on IA No.IV (Order VII Rule 10 r/w Section 151 CPC) and Section 34 petition.
What did the court decide?
Appeal disposed of: order dated 16.07.2024 on IA No.I in AP No.79/2023 set aside; IA No.I allowed and delay of 25 days in filing the Section 34 petition condoned; IA No.IV and the Section 34 petition restored to the District Judge to be considered and decided in accordance with law; no costs; IA No.1/2024 disposed of as infructuous.