The Executive Engineer v. Lakshmegowda
Case brief
What is this about?
Keywords: Section 54(1) Land Acquisition Act 1894 appeal; Section 18 reference; enhancement of compensation; market value re-determination; Rs.1,00,000/- per gunta versus Rs.42,800/- per acre; valuation without sale deed or expert opinion; reliance on judgment in another LAC as comparable (Exs.P19, P20); parity/equal treatment of land losers; same preliminary notification dated 03.09.2009; Kamasamudra Lift Irrigation project; Muthige Village and Huluvare Village, Shantigrama Hobli, Hassan; LAC No.152/2012 attained finality; Manoj Kumar (2018) 13 SCC 96 distinguished; gunta measurement; Karnataka HC Division Bench. Outcome: Miscellaneous First Appeal dismissed, no order as to costs.
What did the court decide?
None - appeal dismissed with no order as to costs; the Reference Court's re-determination of compensation stands affirmed. ¶55