Sri. a C Ananthaswamy v. Nandhi Infrastructure Corridor Enterprises Limited
Case brief
What is this about?
Temporary injunction; prima facie case; balance of convenience; irreparable loss; Order XXXIX Rules 1 and 2 r/w Section 151 CPC; Order 43 Rule 1(r) CPC; MFA; Land Tribunal occupancy rights; Section 10 Mysore (Personal & Miscellaneous) Inams Abolition Act, 1954; Section 28(1)/28(4)/28(6) Karnataka Industrial Areas Development Act, 1966; KIADB; SLAO; BMICP (Bangalore-Mysore Infrastructure Corridor Project); Sy.No.47 Pantarapalya Village, Kengeri Hobli, Bengaluru South Taluk; 24 acres 34 guntas; 18 acres 34 guntas; 6 acres; NANDHI Infrastructure Corridor Enterprises Limited; W.P.No.8706/2025; identification, demarcation and handover directions; XLII Addl. City Civil and Sessions Judge, Bengaluru.
What did the court decide?
Temporary injunction granted over the suit schedule property to the extent of 18 acres 34 guntas (excluding the 6 acres acquired for the BMICP project); directions issued to the Special Deputy Commissioner (KIADB)(BMICP) and the Special Land Acquisition Officer-1 (KIADB)(BMICP) to identify and demarcate the exact 6-00 acres in the plaintiff's presence and hand them over to the defendant, without prejudice to and subject to the outcome of W.P.No.8706/2025.