The Chief Engineer and Anr. v. Aanandkumar and Ors.
Case brief
What is this about?
Procedural dismissal for non-compliance with office objections. Keywords: MFA No.201821/2023 (LAC); Land Acquisition Act Sec.54(1); LAC No.3/2013; judgment and award dated 18.12.2014; Senior Civil Judge Aland; Chief Engineer KNNL IPC Zone Gulbarga; Executive Engineer KNNL Amarja Division; Deputy Commissioner Gulbarga; Special Land Acquisition Officer M & MIP; office objections; default dismissal; Kalaburagi Bench; Justice C.M. Joshi; dated 04.03.2025. No substantive adjudication of compensation; no precedents discussed; no costs or amounts awarded.
What did the court decide?
Two weeks' time was granted to comply with office objections; upon non-compliance by counsel for the appellants, the appeal stood dismissed without further reference to the Court. ¶35