Gogga Channabasavaraj S/O Gogga Channabasayya v. the Special Land Acquisition Officer
Land Acquisition – Enhancement of compensation
Case brief
What is this about?
Enhancement of land acquisition compensation – Railway line Munirabad–Mehaboobnagar project, notification dated 30.07.2009 – lands in Gangavathi taluk, Koppal district (acquiring officers at Sindhanur/Raichur) – reference Court award of Rs.800 per sq.ft. in LAC No.8/2014 & LAC No.9/2014 (judgment dated 07.12.2015, Senior Civil Judge, Gangavathi) enhanced/re-determined to Rs.2,200/- per sq.ft. following MFA No.100355/2016 (finality: review RP No.100097/2022 rejected 21.02.2024; Supreme Court dismissal 09.09.2024) – claimants Gogga Channabasavaraj and Gogga Gurusiddayya v. Deputy Chief Engineer, South Western Railway, SLAO and Deputy Commissioner Koppal – MFA Nos.100116 & 100117 of 2016 allowed in part with cost; MFA Crob Nos.100142 & 100143 of 2018 rejected – statutory benefits and interest payable – Karnataka HC Dharwad Bench, DB, 05.08.2025.
What did the court decide?
MFA No.100116/2016 and MFA No.100117/2016 allowed in part with cost; compensation of the lands re-determined at Rs.2,200/- per sq.ft. with all statutory benefits and interests as per law; cross objections in MFA Crob Nos.100142/2018 and 100143/2018 rejected.