Sri Prakash Ramachandra Sapkal, v. Power Grid Corporation of India Ltd.
Case brief
What is this about?
Landowner sought compensation for a power transmission line and tower installed on his land; the representation was pending despite a third party's counterclaim. The High Court directed the respondent to consider the representation dated 06.03.2023 after hearing the petitioner, within three months.
What did the court decide?
Respondent directed to consider representation dated 06.03.2023 after hearing petitioner, within three months.