M/S Hemanth Enterprises v. Additional Chief Secretary to Government
Case brief
What is this about?
Writ petition challenging BBMP notices issued to a solid waste management contractor alleging poor work performance. The court directed BBMP to consider the contractor's reply to both notices within three weeks and protected the contract's performance in the interim.
What did the court decide?
BBMP to consider petitioner's reply within three weeks; interim protection from disturbance of contract till then; contentions open.