A school facing BBMP demolition orders for constructing an unauthorised additional floor sought quashing of those orders. The court noted its Section 240(8) regularisation application was pending and disposed of the petition directing deferral of action until that application is decided within three months.
What did the court decide?
Respondents directed to defer further action on demolition orders until the Section 240(8) application is considered by the second respondent within three months.