M/S at and S India Private Limited v. the Regional Provident Fund Commissioner-I
Case brief
What is this about?
An employer challenged EPF demands for damages under Section 14B and interest under Section 7Q, with appeals already pending before the CGIT. The High Court disposed of the writ petition, directing the authority not to precipitate the matter till the CGIT determines the applications.
What did the court decide?
Direction to respondent-authority not to precipitate the Section 7Q or Section 14B demands till determination by the CGIT.