The Executive Engineer (Ele) v. Smt. Gangamma
Case brief
What is this about?
KPTCL challenged enhanced compensation awarded for trees removed in drawing a transmission line over land. The High Court found the compensation for coconut and teak trees excessive, reassessed it, and reduced total compensation to Rs.48,450/-, modifying the Trial Court's order.
What did the court decide?
Writ allowed; Trial Court order modified; claimant entitled to Rs.28,482/- balance with 6% interest; KPTCL to deposit within six weeks.