G.V.P.R. Engineers Ltd. v. Hubli Electricity Supply Company Ltd.
Case brief
What is this about?
The High Court quashed an official memorandum blacklisting a contractor and ordering recovery due to violation of natural justice, specifically the failure to serve the enquiry report before passing orders.
What did the court decide?
The impugned official memorandum dated 18.02.2015 is quashed. Respondent No.3 must furnish the special team report to the petitioner for explanation.