B Abdul Rashid v. the State of Karnataka
Case brief
What is this about?
Commission agent allotted an R-type site under a lease-cum-sale agreement challenged a forfeiture notice alleging delayed construction. The court found construction was completed despite delay and substantial investment was made, quashed the forfeiture notice and directed issue of completion certificate and sale deed.
What did the court decide?
Impugned forfeiture notice dated 05.10.2021 (Annexure-A) quashed; Respondent No.3 directed to issue completion certificate and execute sale deed per Rule 20, levying penalty if any, within eight weeks