schedule property and the said suit came to be decreed on 09.08.2017, whereby, it is held that, the plaintiff/petitioner is entitled for 1/5th share in the suit schedule property. Thereafter, the plaintiff/petitioner filed FDP No.25 of 2017 seeking passing of final decree in terms of the preliminary decree passed in OS No.335 of 2010. The Trial Court, after the considering the report of the Court Commissioner, accepted the same, and thereby, allowed the petition as per order dated 03.01.2023. Being aggrieved by the same, the respondent Nos. and 2 have filed RA No.36 of 2023 before the First Appellate Court. The said appeal was resisted by the respondents therein. The First Appellate Court, after re-appreciating the facts on record, by its judgment and decree dated 15.12.2023 dismissed the appeal and confirmed order passed by the trial Court in FDP No.25 of 2023. Being aggrieved by the judgment and decree passed by the