The Executive Engineer v. Shri Dundappa Gadigeppa Galabi
Case brief
What is this about?
State appealed a land acquisition compensation enhancement after 937 days' delay. Holding that Section 74(1) RFCTLARR Act's 120-day outer limit is mandatory and admits no condonation beyond it, the court rejected the condonation application as not maintainable and dismissed the appeal.
What did the court decide?
Condonation application rejected as not maintainable; appeal dismissed; deposit ordered transmitted to the Reference Court for release to claimants.