Sri Ayyapu Reddy S/O. Nagireddy v. the Deputy Chief Engineer
Case brief
What is this about?
This writ petition challenged a termination notice and sought mandatory relief for pending payments and site handover. The Court quashed the termination notice, granting the petitioner five months to complete the remaining 67% of work, but clarified that no further clearances were required and the respondent could initiate action if the deadline was missed.
What did the court decide?
The termination notice is quashed; the petitioner is granted five months to complete the work, though no further clearances are required.