M/S Concept Technologies v. Karnataka Industrial Area Development Board
Case brief
What is this about?
This writ petition challenged a penalty order for delayed construction under a lease-sale agreement. The court granted five months to pay the penalty, considering the pandemic, and directed the respondents to issue clearance and possession certificates, subject to payment.
What did the court decide?
Petitioner granted five months to pay Rs.21,00,393/- penalty; respondents directed to issue clearance and possession certificates upon payment; 6% p.a. interest applicable if unpaid.