"Construction of First Grade College at Siddlaghatta, Kolar District", the plaintiff submitted his bid and was the successful bidder. A work order was issued in his favour and an agreement was executed on 26.3.1993. The cost of the work under the said agreement was Rs.38,91,629/-. The plaintiff was required to commence work on 26.3.1993 and complete the construction work on or before 26.3.1995. It was further pleaded that in view of the delay, on the part of the defendants in supplying approved working drawings, shifting of high tension electric, telephone lines etc. and non-availability of essential building materials and irregular payments for the work done by him under the contract, he was not in a position to complete the work within the specified period of time in the contract. It was further pleaded that unilateral rescission of the contract by the defendant without extending the period for completion of the contract is illegal and as such the defendants are liable to indemnify the plaintiff for the loss caused to him. Hence, the suit.