M/S.Eskaps India Pvt.Ltd. through Its Director v. Bihar State Electricity Board
Case brief
What is this about?
Jharkhand HC (Ranchi), W.P(C) No. 364 of 2005, decided 28.01.2026 by Sujit Narayan Prasad, J. Contractor M/s Eskaps India Pvt. Ltd. sought Article 226 direction for payment of Rs.4,36,725/- plus 18% interest from April 1999 for amounts withheld despite satisfactory completion of work. Court noted arbitration Clause-8.0 in Article of Agreement (Annexure-2) with Bihar State Electricity Board (successor entity after bifurcation: JUVNL), disputes referable to Chairman, BSEB per Clause 26 of Tender document; earlier representation Annexure-5 dated 26.03.2003. Disposition: writ petition disposed of with liberty to petitioner to apply to Chairman-cum-Managing Director, JUVNL for appointment of Arbitrator within six weeks; all disputes including apportionment of liability to be adjudicated by Arbitrator; pending I.As disposed. Keywords: arbitration clause, appointment of arbitrator, liberty to seek arbitration, withheld payment, electricity board bifurcation, JUVNL, BSEB, PVUNL, Article 226.