Gita Devi v. the State of Jharkhand
Case brief
What is this about?
Statutory interest for delayed payment of land acquisition compensation under the Land Acquisition Act, 1894 (Sections 18 and 28A); L.A. Case No.16/2007-08; compensation paid 30.04.2024 with interest only till 28.06.2018; SLAO Tenughat Project, Hazaribag letter No.171 dated 02.07.2025 to Executive Engineer, Waterways Sub-Division, Barhi for fund allotment for 15 awardees; writ petition disposed of with directive: representation to SLAO Hazaribagh within three weeks, calculation and disbursement of interest within six weeks thereafter.
What did the court decide?
Directive to the petitioner to submit a representation to the Special Land Acquisition Officer, Hazaribagh within three weeks; upon receipt, the authority to calculate and disburse the unpaid statutory interest within six weeks thereafter. ¶29