Ms Aditya And Rashmi Construction Through Its Managing Director Ashok Kumar Singh v. Road Construction
Case brief
What is this about?
Infructuous closure of writ petition: Aditya and Rashmi Construction Pvt Limited v. State of Jharkhand and others (Road Construction Department officials; District Certificate Officer, Sahebganj), W.P.(C) No. 277 of 2016, decided 21.04.2025 (2025:JHHC:11702-DB) by Chief Justice M. S. Ramachandra Rao and Justice Rajesh Shankar. Challenge to cancellation of contract (granted 29.09.2015) held infructuous because the work stood executed by a third party; petition closed with liberty to pursue other claims in the appropriate forum. No statutory provisions or precedent cases cited; no monetary award.
What did the court decide?
Writ petition closed as infructuous; liberty granted to the petitioner to make any other claims in the appropriate forum, if so advised. ¶18