Naveen Dubey v. the State of Jharkhand through the Chief Secretary Road Construction Department Jharkhand Ranchi
Case brief
What is this about?
Infructuous writ petition dismissed; Jharkhand High Court Ranchi; W.P. (C) 1114 of 2024; petitioner Naveen Dubey; respondents State of Jharkhand, Road Construction Department, Water Resource Department (Secretary, Chief Engineer), Executive Engineer Mechanical Division Mandal Latehar; tender issued 27.05.2023; work to be completed within 300 days; cause no longer survives for adjudication; no counsel for petitioner; State counsel Piyush Chitresh, A.C. to A.G.; decided 10.07.2025.
What did the court decide?
The cause in the Writ petition no longer survives for adjudication, since the tender in question was issued on 27.05.2023 and the work was to be completed within 300 days. ¶13