Badhan Bedia v. State of Jharkhand through Deputy Commissioner
Case brief
What is this about?
F.A. Nos. 164, 165, 172 & 153 of 2018, High Court of Jharkhand (Anubha Rawat Choudhary, J., 02.05.2025): batch enhancement of land-acquisition compensation for Village Kadru/Karru, District Ramgarh (L.R. Case Nos. 73/2012, 100/2012, 74/2012, 95/2012; respondents include Deputy Commissioner, Ramgarh and Deputy Chief Engineer (Const.) East Central Railway); rate enhanced from Rs.3,000/- to Rs.7,000/- per decimal with solatium and other benefits under the Act, in terms of judgment dated 25.03.2025 in F.A. No. 176 of 2018 and other analogous cases (Masmohna village comparison, notification dated 03.04.2003); appeals allowed, awards modified as to rate only; no order as to costs; pending I.As closed.
What did the court decide?
First appeals allowed; impugned judgement modified only with respect to the rate of compensation — compensation enhanced from Rs.3,000/- to Rs.7,000/- per decimal for all classes of land, with solatium and other benefits as admissible under the Act; no order as to costs; Office to prepare decree; pending I.As, if any, closed; copy of judgment and appellate decree to be communicated to the court concerned through e-mail/FAX.