Mithun Kumar Gupta v. the State of Jharkhand
Case brief
What is this about?
Contractor sought payment of Rs.21,88,369/- for a completed Amrit Sarovar pond construction work certified satisfactory by engineers. The Court held the writ court can direct payment of an admitted amount and disposed of the petition directing the petitioner to file a fresh representation before the Deputy Commissioner, who must decide and pay within fixed periods or pass a reasoned order.
What did the court decide?
Direction to submit fresh representation to respondent no.3; decision and payment within four weeks if payable, else reasoned order.