The State of Jharkhand through the Deputy Commissioner v. Ms Bharat Drilling and Foundation Treatment Pvt. Ltd.
Case brief
What is this about?
High Court of Jharkhand, Commercial Appeal No. 17 of 2019, order dated 28.08.2024 (Anubha Rawat Choudhary, J.): State of Jharkhand (PHED) v. M/s Bharat Drilling & Foundation Treatment Pvt. Ltd. — condonation of delay of 4001 days refused; Section 37(1)(b) Arbitration and Conciliation Act 1996 appeal governed by Article 116 Limitation Act 1963 (90 days); Borse Brothers (2021) 6 SCC 460 followed; Consolidated Engg. Enterprises (2008) 7 SCC 169 referred; delay beyond limitation condonable only exceptionally; Section 34 challenge to award dated 23.08.2000; Execution Case No. 08 of 2001; appeal and IA No. 10565 of 2019 dismissed.
What did the court decide?
The contention that Section 37(1)(b) of the Arbitration and Conciliation Act, 1996 prescribes no limitation for filing an appeal against a Section 34 judgment is misconceived; the period of limitation for filing an appeal in the High Court is governed by Article 116 of the Limitation Act, 1963, namely 90 days from the date of the decree or order.