Kumar Niwas, Bright Lane, Koker, Ranchi (RPCL) at Rs.276.5 Crores vide Agreement Nos. 01/ RE/RITES/ 03-04 to 10/ RE/ JEITES/ 03-04. It is further alleged in the FIR that in terms of the provision of agreement executed between the RITES Ltd. and M/s. RPCL bank guarantees were required to be submitted by M/s. RPCL on account of security deposit at the rate of 5% of Rs.277.5 Crores which comes to the tune of Rs.13.875 Crores of contract amount in the form of Bank Guarantee at the time of signing of agreement. The M/s. RPCL submitted the bank guarantee of Rs.15,91,02,019/- to RITES Ltd. as cover for security deposit and M/s. RPCL also submitted bank guarantee for Rs.16,80,48,772/- to RITES Ltd. as cover for mobilization advance. All the aforesaid bank guarantee were submitted by Sri A.K. Singh, CMD of M/s. RPCL & Sri D. K. Das, Construction manager, RPCL. The further case of the prosecution is that upon receipt of bank guarantees from M/s. RPCL, confirmation was obtained by RITES Ltd. from Bank of India who issue the said bank guarantees vide their various letters of confirmations. It is further alleged that receipt of confirmation of Bank of India the aforesaid Bank guarantee were issued by them and the net value of mobilization advance which come to the tune of Rs.16.8 Crores was paid to M/s. RPCL. On being checked with Bank of India, Club Side, Ranchi, regarding error in date in one of the Bank guarantee i.e. CBS: BG:/ 04-05: 30/25, it has been informed by the Bank that the said Bank guarantee has already been surrendered by M/s. RPCL and cancelled on 13.09.2004 and it was done without seeking any advise from RITES Ltd., the beneficiary of guarantee.