4. On the contrary, the learned counsel for the respondents submits that the petitioner has delayed the work alleging that the sanctioned site map was not provided to it, whereas the actual fact is that the petitioner was not at all interested in sincerely executing the work within the stipulated time. Though the sanctioned map of the construction site was ready with the respondent-Corporation, yet the petitioner did not approach the concerned authority for receiving the same. The respondent no. 4 vide letters dated 09.09.2008 and 06.10.2008 apprised the petitioner that information was telephonically given to collect the sanctioned map, but no one appeared to collect the same. Though the petitioner made several representations before the authorities of the Corporation for providing the sanctioned map, yet even after repeated information, the same was not collected from the office of the Corporation which clearly indicates that the petitioner was deliberately delaying the construction work. Since the progress of the work was found to be quite slow, penalty was also imposed against the petitioner. The respondent no. 4 vide letter no. 891 dated 17.09.2008 directed the petitioner to complete the work within the stipulated period mentioned in the agreement and work order. It was also informed that the progress of the work was not proportionate to the time stipulated in the work order. Several letters in this regard were issued to the petitioner including letters dated 12.04.2008, 06.05.2008 and 17.09.2008, however, since the petitioner did not expedite the construction work inspite of several intimation, the Executive Engineer, Hazaribagh Division, Hazaribagh, vide letter no. 939 dated 29.09.2008 directed the petitioner to start the work by 03.10.2008, otherwise the agreement would be rescinded and the petitioner would be blacklisted. The Executive Engineer, Hazaribagh Division, Hazaribagh intimated the petitioner vide letter no. 1160 dated 23.12.2008 that the work had already gone five months beyond the scheduled date of completion of work i.e., 21.07.2008, but the progress of the work was quite slow. In the said letter also, the petitioner was directed to expedite the progress of the work, failing which appropriate action including the cancellation of agreement would be taken against it. However, the petitioner did not pay