Ms Sunny Construction And Co. Through Its Partener Namely Sanjay Rampal v. Road Construction
Case brief
What is this about?
Three writ petitions filed by a government contractor challenging non-payment and non-measurement of road works. The court noted the claim requires factual determination and directed the Superintending Engineer to verify records and decide on payment and security release within 12 weeks after receiving a fresh representation.
What did the court decide?
Liberty to prefer fresh representation; Superintending Engineer to verify records and decide on payment and security release within 12 weeks.