Ms Kashyap Construction Co. Ltd. through Its Managing Director Shri Santosh Kumar v. Water Resources Department
Case brief
What is this about?
In a public interest context, the High Court of Jharkhand disposed of a writ petition challenging a decision to terminate a construction contract. The Court found the termination communication premature and directed the respondent to measure completed work and pay due amounts within six weeks, citing land compensation delays as the cause.
What did the court decide?
The petitioner is entitled to a final measurement of work done. If any amount is found due to the petitioner, the same shall be paid within six weeks.