Saurya Construction Pvt. Ltd. through Its Director Rajendra Prasad Singh v. Water Resources Departement
Case brief
What is this about?
Single judge order listing W.P.(C) No. 2884 of 2013 for counter affidavit; interim order dated 24.07.2013 continued pending the reply.
What did the court decide?
Allow two weeks time for counter affidavit; interim order dated 24.07.2013 to continue.