Zafar Ahmed v. Ut of J and K Th Commissioner Secretary to Govt Public Work Department and Others
Case brief
What is this about?
Contract-rate disparity writ, J&K & Ladakh HC (Jammu), 08.11.2025, Moksha Khajuria Kazmi J: Class-'A' contractor Zafar Ahmed v. UT of J&K and PWD (R&B) officers; work order SE/DB/32-34 dt. 19.01.2024 under e-NIT 1 of 2023-24 dt. 27.10.2023 for 2 km link road; prayers to terminate contract priced below SoR 2023-24, revise rates (or grant 2022 rates on analogy) or re-tender at current SoR; disposed of at threshold - petition treated as representation, speaking order directed within 4 weeks against proper receipt; no substantive issue decided, no statutes or precedents cited, no costs or quantum.
What did the court decide?
Petition disposed of at the threshold; respondents directed to treat it as a representation and decide it by a speaking order within four weeks of receiving a copy of the order with the complete set of the writ petition, against proper receipt.