Sher-E-Kashmir Institue of Medical Sciences through Its Director v. M/S Siemens Pvt. Ltd.
Case brief
What is this about?
Section 34 setting-aside petition; J&K Arbitration and Conciliation Act 1997; public policy of the State; patent illegality; fundamental policy of Indian law; ONGC v. Saw Pipes; Associate Builders v. DDA; OPG Power v. Enexio; existence of arbitration agreement; NIT vs formal agreement; jurisdictional objection waived; turnkey supply order; installation and site-preparation charges; medical equipment supply (X-ray, 64-slice CT scanner, CT stimulator); Measurement Book employer's duty; completion certificate; HOD Radiology certificate; limitation plea raised first time at final arguments; deemed waiver; stale claims; SKIMS v Siemens; Commercial Division Srinagar.
What did the court decide?
No relief to petitioner: all three Section 34 petitions dismissed as meritless; the three awards dated 23.11.2022 (installation expenses with simple interest @6% p.a. from 21.10.2009 to date of award and @9% p.a. from date of award till payment) stand undisturbed; record to be sent back.