Makholi Ram v. the State of Hp and Others
Case brief
What is this about?
Chamera Hydro Electric Project Stage-II; Resettlement and Rehabilitation Scheme Part-XII; employment to one member of affected family; land acquisition District Chamba 2000-2002; compensation paid; delay and laches; Deputy Commissioner authorized officer; Karam Chand v. State of H.P.; National Hydro Electric Corporation Ltd.; LPA No. 214/2016; SLP(C) No. 14431/2023; disposal with direction to decide within eight weeks; rights and contentions left open; Himachal Pradesh High Court CWP 2026; Jyotsna Rewal Dua.
What did the court decide?
Writ petitions disposed of with direction to respondent No.4-Deputy Commissioner, Chamba (authorized officer under the Scheme) to consider and decide the petitioners' cases within eight weeks; all rights and contentions left open (including delay and laches and eligibility); orders to be communicated to the petitioners; pending miscellaneous applications disposed of.