M/S Seagull Laboratories Pvt. Ltd. v. Hpsebl and Others
Case brief
What is this about?
Electricity Act 2003; Section 126 assessment order; Section 127 appeal; Section 127(2) pre-deposit of half assessed amount; appeal dismissed in default; restoration application Order 9 Rule 9 with Section 151 CPC; condonation of delay; HPSEBL; electricity disconnection; revival of appeal on deposit; interest at 6% per annum; Divisional Commissioner Kangra at Dharamshala; interim stay order balance of convenience. Relevant where an appellate authority refuses restoration of a long-pending statutory appeal for want of pre-deposit although the appeal was earlier entertained without the deposit and interim relief subsisted.
What did the court decide?
Writ petition disposed of with directions: petitioner at liberty to deposit the balance assessed amount in terms of Annexure P-2 and as per Section 127(2) of the Electricity Act with respondents-HPSEBL within three weeks, along with interest at 6% per annum from due date; on such deposit the appeal before the Divisional Commissioner stands revived upon a formal application; petitioner may seek restoration of electricity connection before the Appellate Authority; Appellate Authority to endeavour to dispose of the appeal preferably within four months; pending miscellaneous application(s), if any, also disposed of.