Saran Dass v. the State of Hp and Others
Case brief
What is this about?
A street vendor sought to quash road-infrastructure enforcement notices and protect her existing vending activity while an alternate vendor site and rehabilitation process were developed. Without deciding the merits, the Court permitted a fresh representation to the Municipal Council and directed consultation with the relevant stakeholders. The Council was to decide the representation within three weeks, and no coercive action was to be taken meanwhile.
What did the court decide?
The petitioner may make a fresh comprehensive representation to respondent No. 7 within one week. Respondent No. 7 must consult the relevant stakeholders and decide it within three weeks, communicating the decision to the petitioner. No coercive action may be taken under the impugned notice meanwhile; pending miscellaneous applications stand disposed.