M/S Garg Sons Estate Promoters Pvt. Ltd. v. the State of Hp and Others
Case brief
What is this about?
The petitioner, a Class-A contractor, completed construction work in May 2025, but the final bill was not prepared even after the defect liability period lapsed in May 2026. The High Court directed respondent No. 3 to prepare and verify the final bill within one month and make payment after contractual adjustments within four months, disposing of the petition without adjudicating the merits.
What did the court decide?
Direction to respondent No. 3 to prepare and verify the final bill within one month and make payment after adjustments within four months.