Sunder Singh v. Union of India and Others
Land acquisition – National Highways Act, 1956, S.3-A
Case brief
What is this about?
Himachal Pradesh High Court, Shimla; Sunder Singh v. Union of India and others; CWP No.10474 of 2023; decided 08.04.2026; Jyotsna Rewal Dua, J. Keywords: Section 3-A National Highways Act 1956; NH-22/NH-5 Shimla-Parwanoo four-laning; incomplete land acquisition compensation; Khasra No.198/98/51/44/6 Mohal Bara Solan; 01 biswa acquired of 04 biswas; Award No.21/B 21.07.2020; Kanungo demarcation 05.10.2020; court-ordered Tehsildar demarcation 23.09.2025; NHAI road widening; CALA Solan; direction to acquire remaining land and pass award within four months; writ petition allowed.
What did the court decide?
Respondents including NHAI and respondent No.4 (Competent Authority Land Acquisition, Solan, District Solan, H.P.) directed to acquire the petitioner's remaining land (03 biswas in Khasra No.198/98/51/44/6) and pass the award in accordance with law as expeditiously as possible, not later than four months; pending miscellaneous applications disposed of.