Ashwani Kumar and Another v. Union of India and Others
Arbitration and Conciliation Act, 1996 – Section 29-A (5)
Case brief
What is this about?
Section 29-A (5) Arbitration and Conciliation Act 1996; extension of time for completion of arbitration proceedings; expiry of statutory time limit for arbitral award; arbitrator closed proceedings after pleadings completed; Section 3 National Highways Act 1956 arbitrator; Divisional Commissioner Shimla; land acquisition District Solan H.P. for National Highway; Arbitration Case No. 400/2018; Reference Petition filed 2018; award by competent authority; direction to conclude proceedings and pass award on or before 6th September 2026; High Court of Himachal Pradesh; Arb. Case No. 591/2024; Romesh Verma Judge; Union of India respondents.
What did the court decide?
Extension of time granted: the Arbitrator-cum-Divisional Commissioner, Shimla was directed to conclude the arbitral proceedings in Arbitration Case No. 400/2018 and pass the arbitral award on or before 6th September, 2026.