Netar Singh v. Special Land Acquisition Officer and Others
Arbitration and Conciliation Act, 1996 – Section 29(4)
Case brief
What is this about?
Extension of time for arbitration proceedings; Section 29(4) Arbitration and Conciliation Act 1996; Section 3 National Highways Act 1956; land acquired in District Mandi H.P. for National Highway construction; Arbitration Reference Case No.156/2019; Neter Singh vs. Special Land Acquisition Officer; Divisional Commissioner Mandi as Arbitrator; statutory time limit for award elapsed; proceedings closed after completion of pleadings; onus on Arbitrator to complete within prescribed time schedule; delay must be bonafide and explainable; direction to conclude proceedings and pass award on or before 10.09.2026; petition disposed of; High Court of Himachal Pradesh; Romesh Verma, Judge.
What did the court decide?
Extension of time effectively granted: the Arbitrator-cum-Divisional Commissioner, Mandi, H.P. is directed to conclude the arbitral proceedings and pass the arbitral award in Arbitration Reference Case No.156/2019 on or before 10th September, 2026.