High Court of Himachal Pradesh, Shimla; Arb. Case No. 8/2026; decided 06.03.2026; Justice Romesh Verma (oral); M/s. Ajay M/C Tools v. Central Public Works Department; Section 29-A(4)/29A(4) Arbitration and Conciliation Act 1996; extension of time for passing of arbitral award; Annexure A-5 arbitrator's order dated 14.12.2025; eye ailment of Arbitrator; GST model calculation and 10C claim calculation sheet; order dated 26.04.2025; six weeks' extension; petition disposed of.
What did the court decide?
Extension of six weeks' time, from 06.03.2026, for passing of the final award by the learned Arbitral Tribunal. ¶20